Building permits issued within the Town of Knightdale receive inspections from multiple agencies - Knightdale Public Works, Knightdale Development Services, Wake County Planning & Development Services, and Knightdale Fire.
Both Wake County and Town of Knightdale complete next business day inspections.
The cut-off time for requesting next-day inspections is 3 p.m. (effective Monday, January 13, 2025). To schedule an inspection for the next business day, your request must be submitted before 3 p.m. of the previous business day.
The following inspections are performed by Town of Knightdale staff and scheduled via the Wake County Permit Portal. Click on each heading for additional information and sample checklists. Some elements may vary depending on the type of project and building permit.
A Perimeter Erosion Controls inspection is required on all new single family homes and new non-residential buildings. It is the initial sedimentation and erosion control (S&EC) inspection to ensure all required erosion control measures are present. This inspection is required before the Setback Inspection.
Individual Lot:
Whole Site:
*performed by Knightdale Public Works
A setback inspection is required for any new structures or expansion of existing structures. This is one of the first inspections scheduled for a building permit to ensure the structure is located correctly on the lot. The setback inspection must be completed prior to a footing inspection being scheduled.
*performed by Knightdale Development Services
This inspection is scheduled after the forms have been set, but before any concrete is poured.
Driveway
Sidewalk
*performed by Knightdale Public Works
A Final Site Stabilization inspection is required on all new single family homes and new non-residential buildings. It is the last S&EC inspection to ensure site is stabilized and free of erosion or drainage issues. This inspection must take place before a CO will be issued.
The final inspection made by the Town to ensure that all zoning issues have been addressed prior to issuance of a Certificate of Occupancy (or Completion). This inspection is scheduled after Wake County passes the Building Final.
*performed by Knightdale Development Services
All building, plumbing, electrical, and mechanical inspections are completed by the Wake County Permits & Inspections on behalf of the Town.
Fire related inspections are scheduled by contacting the Knightdale Fire Marshal directly by either phone or email. These inspections are not scheduled via the Permit Portal.