Craften Kitchen (ZCP-5-20)

Milestone timeline:

First Official Submission
Completed: Jul 7, 2020
Sketch Plan
Development Review Committee Approval
Completed: Sep 10, 2020
Master Plan
Allowed for Demolition to Begin
Completed: Apr 13, 2021
Pre Construction Meeting
Returned with Comments
Completed: Jun 8, 2021
Construction Drawings

A proposed 3,100 square foot food court at 706 Money Ct. The use is permitted by right in the Highway Business zoning district. DRC reviewed and approved the Master Plan at the September 10, 2020 meeting. Construction Drawings were approved November 19, 2020 but were recently re-submitted to include a second story covered patio. The applicant has submitted a building permit application, which is currently under review.  

Project Updates